Damages For Defective Works - Management Time & Loss Of Profit

Claims for damages for breach of contract often include components for both management time and loss of profit. The Technology and Construction Court has recently considered the principles concerning the recovery and assessment of these two types of damages.

United KingdomLitigation, Mediation & Arbitration
Adrian Bell
Adrian Bell

Claims for damages for breach of contract often include components for both management time and loss of profit. The Technology and Construction Court has recently considered the principles concerning the recovery and assessment of these two types of damages. In Bridge UK.Com Limited v Abbey Pynford plc [2007] EWHC 728 (TCC), the claimant sought to recover damages for the defective installation of a foundation for its printing press.

Management time

A claimant will usually include as part of its claim, the costs of its senior staff in dealing with a breach of contract. Effectively, the claimant is seeking to be compensated for the diversion of its employees from revenue generating activities in order to attend to the consequences of the breach.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from