Court Of Appeal Reviews LADs Provisions In JCT Contract

The JCT standard form of contract provides a specific contractual mechanism for deduction of Liquidated and Ascertained Damages ("LADs") by the employer in certain circumstances if the construction project is not completed on time (as do many other standard form construction contracts, although the procedure in the JCT is more complicated than most).

United KingdomLitigation, Mediation & Arbitration
Julian Bailey
Julian Bailey
Nirada Griffith
Nirada Griffith

The JCT standard form of contract provides a specific contractual mechanism for deduction of Liquidated and Ascertained Damages ("LADs") by the employer in certain circumstances if the construction project is not completed on time (as do many other standard form construction contracts, although the procedure in the JCT is more complicated than most). In a recent case before the Court of Appeal the question was whether, if the employer had followed the procedure laid down in the contract for deduction of LADs, the later extension of time granted by the architect could render that (previously valid) deduction of LADs unlawful.

The court answered this question in the negative. The employer’s right to deduct LADs crystallised when it issued the notice of its intention to deduct LADs. Even though the architect had subsequently granted an extension of time (which effectively reduced the amount of LADs payable), it did not follow that the original notice of intention to deduct LADs was

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from