Where
a party terminates a contract for repudiatory breach, a damages
award should place it in the position it would have been in had the
contract been properly performed. Assuming the contract was a
profitable one, there are two alternative measures of loss which
might be sought: 1) "expectation loss" (the financial
benefit which the non-defaulting party expected from the contract,
e.g. increased profits or reduced expenditure); or 2)
"reliance loss" (the wasted costs incurred in the
expectation of the financial benefit, e.g. payments to the
counterparty, third parties and internal costs).
In CIS General Insurance Ltd v IBM United Kingdom Ltd
[2021] EWHC 347 (TCC), O'Farrell J analysed
the authorities on the two measures of contractual loss. She held
that, although the two methods for quantifying loss of bargain are
different, there is no change in the underlying characteristics of
the losses for which compensation is sought. Here, this meant that
a claim for