Share on LinkedInShare on LinkedIn

ARTICLE · 31 JANUARY 2011

Commercial Court Reviews Law On Breaking The Chain Of Causation, Mitigation And Remoteness Of Damage

G sold a cargo of butane to B to be used as feedstock by B in its plastics production plant.

United KingdomLitigation, Mediation & Arbitration

Borealis AB v Geogas Trading SA [2010] EWHC 2789 (Comm)

Dispute

G sold a cargo of butane to B to be used as feedstock by B in its plastics production plant. The butane was contaminated with fluorides, which cracked during processing to form hydrofluoric acid, which in turn triggered a pH alarm at the plant. B took no action in response to the alarm. The acid in the system caused substantial physical damage to the plant, in particular corrosion to the heat exchangers, causing a gas leakage. Production time was lost in the immediate aftermath whilst damaged parts were refitted and at further times during the following year. B claimed loss of profits from plant down time.

G admitted that the contaminated butane was not fit for its purpose and that it had breached the supply contract. However, G argued that its breach did not cause B's loss. Rather, it contended that B's actions (or inactions) in failing to respond to the pH alarm, investigate the problem and take

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from