Borealis AB v Geogas Trading SA [2010] EWHC 2789
(Comm)
Dispute
G sold a cargo of butane to B to be used as feedstock by B in
its plastics production plant. The butane was contaminated with
fluorides, which cracked during processing to form hydrofluoric
acid, which in turn triggered a pH alarm at the plant. B took no
action in response to the alarm. The acid in the system caused
substantial physical damage to the plant, in particular corrosion
to the heat exchangers, causing a gas leakage. Production time was
lost in the immediate aftermath whilst damaged parts were refitted
and at further times during the following year. B claimed loss of
profits from plant down time.
G admitted that the contaminated butane was not fit for its
purpose and that it had breached the supply contract. However, G
argued that its breach did not cause B's loss. Rather, it
contended that B's actions (or inactions) in failing to respond
to the pH alarm, investigate the problem and take