This appeal arose from the arrangements between the late Claimant and his former solicitors, the Appellant, in respect of proceedings between Mr Farrar and the Defendant Respondent...

United KingdomLitigation, Mediation & Arbitration

Farrar & Anor v Miller  [2022] EWCA Civ 295

11 March 2022

Background

This appeal arose from the arrangements between the late Claimant ('Mr Farrar') and his former solicitors, the Appellant ('CANDEY'), in respect of proceedings between Mr Farrar and the Defendant Respondent ('Mr Miller').  In sum, Mr Farrar and CANDEY had entered into several agreements in respect of the funding of Mr Farrar's claim, starting with a damages-based agreement ('DBA') in October 2013.  On 12 September 2019, this first DBA was replaced by a second DBA; and Mr Farrar and CANDEY further executed a deed by which Mr Farrar assigned all of his claims against Mr Miller to CANDEY ('the Assignment').

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from