Zurich Insurance Plc v Nightscene Ltd: Limitation Issues In Insurance Policy Payments

The claimant insurer issued an insurance policy in 2006 to the purchaser of a new-build home covering building defects. Prior to that, the developer had entered into an Agreement with the insurer,

United KingdomInsurance

Judge considers limitation issues following a payment under an insurance policy

The claimant insurer issued an insurance policy in 2006 to the purchaser of a new-build home covering building defects. Prior to that, the developer had entered into an Agreement with the insurer, whereby it had agreed to correct any notified defects. Clause 4.16 of the Agreement provided that "Where [the insurer] pays any sum relating to the Developer's obligations or responsibilities under this Agreement or a Warranty the Developer agrees that it shall reimburse [the insurer] with all of the reasonable associated costs [the insurer] incurs in so doing".

The insurer had also entered into a guarantee with the developer's parent company (the guarantor).

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from