Court Of Appeal Rules On Applicability Of QOCS Where Settlement Is Reached Via Tomlin Order

Cartwright v Venduct Engineering Ltd [2018] EWCA Civ 1654

United KingdomInsurance

Cartwright v Venduct Engineering Ltd [2018] EWCA Civ 1654

The Court of Appeal has upheld a first instance decision confirming that a successful defendant can recover costs from damages payable to a claimant by an unsuccessful co-defendant in the same proceedings.

However, such a recovery is limited to where an order of the court, awarding that sum of damages, has been made.  It is not permissible for a defendant to enforce where the damages have been agreed by a Part 36 offer or in a Tomlin Order, which are not deemed orders of the Court within the ambit of CPR 44.14, standing in contrast to a consent order.

The ruling is good news for insurers and companies in occupational diseases, who are often brought into multi-defendant cases by claimants in hope, rather than expectation, of bringing a successful claim against one of a number of parties.