The Damages Remedy In Public Procurement Claims: Still Alive And Well?

Gowling WLG
Gowling WLG
Contributor
Gowling WLG

Gowling WLG

The firm The firm’s lawyers speak English, French, Russian and Ukrainian. The firm’s client base...

View firm profile
Explore more from Gowling WLG

In Nuclear Decommissioning Authority v ATK Energy EU Ltd (formerly Energy Solutions EU Ltd) [2017 UKSC 34]...

United KingdomGovernment, Public Sector

In Nuclear Decommissioning Authority v ATK Energy EU Ltd (formerly Energy Solutions EU Ltd) [2017 UKSC 34], the Supreme Court ruled that claimants seeking damages for breaches of the Public Contracts Regulations 2006 are only able to do so if the breach is "sufficiently serious".

In the decision, the Court applied the second principle of liability for breaches of Community law from the judgment of the Court of Justice in Francovich v the Italian Republic [1995] ICR 772. This was on the basis that Parliament did not intend to go beyond the right to claim damages under Community law when amending regulations to implement the Remedies Directive in 2009.

What is meant by "sufficiently serious" and will this deter claims for damages in the future? And what will happen to the Francovich principles after the UK leaves the EU?