Today's entry reports on the launch of the Planning
Inspectorate's Consents Service Unit.
Last Monday saw the low-key launch of a new unit in the Planning
Inspectorate (PINS) intended to assist with the co-ordination of
other consents before and during the examination of Planning Act
applications.
Background
When the Planning Act was a twinkle in the (previous)
government's eye, one of its main aims was to reduce the number
of separate consents that were required for the same project.
The oft-quoted Heathrow Terminal 5 project required 37 applications
to be made, and a
very early blog entry analysed whether the Planning Act
would have reduced this to one application (not quite). The
Planning Act was thus intended to be a 'one stop shop' for
consents as far as could be achieved. Quite a few consents,
however, required the agreement of the consenting body before they
could be disapplied by a Development Consent Order (DCO), and in
the early days of the regime,