ARTICLE · 16 SEPTEMBER 2011

New Time Limits For Public Procurement Proceedings

The Public Procurement (Miscellaneous Amendments) Regulations 2011 will come into effect on 1 October 2011.

United KingdomGovernment, Public Sector
Susan Hankey
Susan Hankey
David Marks
David Marks

The Public Procurement (Miscellaneous Amendments) Regulations 2011 will come into effect on 1 October 2011. They change the time limits for bringing public procurement proceedings, and make certain other amendments summarised below. The changes apply to all the public sector, utility sector and recent defence and security public contracts rules, as well as to their relevant Scottish equivalents.

Time limits

The new time limit for bringing procurement proceedings will be 30 days running from the date on which the claimant first knew, or ought to have known, that grounds for starting the proceedings had arisen (the "date of knowledge"), with Court discretion to extend this period up to an absolute maximum of three months. This will apply in all situations where the date of knowledge is 1 October 2011 or later. Transitional arrangements apply so that where the date of knowledge occurs before 1 October 2011, the time limit will be three months from the date of

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from