Do Not Pass Go? Pass/ Fail Questions And Their Consequences

A failure to spell out the consequence of failing a pass/ fail criterion in an Invitation to Tender ("ITT") may mean that an authority cannot reject a tender which fails the criteria.

United KingdomGovernment, Public Sector

A failure to spell out the consequence of failing a pass/ fail criterion in an Invitation to Tender ("ITT") may mean that an authority cannot reject a tender which fails the criteria. As the Court recognised, the judgment has potentially far-reaching consequences for authorities and bidders alike.

MLS (Overseas) Limited ("MLS") brought a challenge against the Ministry of Defence's ("MOD") decision to award a contract worth circa £385 million to a rival tenderer, Shipping Consultants Associated Ltd ("SCA") in respect of various support services to the Royal Navy – including its new aircraft carrier, the Queen Elizabeth. The procurement process was subject to the Defence and Security Public Contracts Regulations 2011, as amended ("DSPCR").

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from