Today's entry looks at progress on secondary consents and
the designation of the Waste Water National Policy Statement.
The Infrastructure Planning Commission (IPC) - or from next
Monday the Secretary of State - gives consent for nationally
significant infrastructure projects. Such consent does not
necessarily allow a spade to be put in the ground the next day,
partly because various other consents are needed that cannot easily
be combined with the main consent under the Planning Act 2008.
To provide some alleviation of this, the government is asking
the bodies that give decisions on these secondary consents to agree
to do so within 13 weeks of an application being made. This is
partly as a result of pressure to streamline infrastructure
consenting and partly as a follow on from the 'Penfold
review', which looked at the myriad of non-planning consents
and whether and how they were used.