ARTICLE · 05 FEBRUARY 2024

High Court Provides Clarification On JCT Contractor Termination Rights And Confirms Dangers Of Getting It Wrong

The recent High Court decision of Providence Building Services Limited -v- Hexagon Housing Association Limited [2023] provided clarification on a contractor's right to terminate...

United KingdomEmployment and HR

The recent High Court decision of Providence Building Services Limited -v- Hexagon Housing Association Limited [2023] provided clarification on a contractor's right to terminate its employment under a JCT Design and Build Contract 2016 ('JCT DB2016').

Facts of the case-

The case was brought by Providence Building Services, the contractor, who was employed by Hexagon under an amended JCT DB2016 contract. Providence had submitted an interim payment application and Hexagon had failed to make payment by the final date for payment. As a result, Providence proceeded to issue a notice of specified default, pursuant to clause 8.9.1.1 of the JCT DB2016. Following the issue of the default notice, Hexagon proceeded to make payment in full, rectifying the default within the 28-day period specified in clause 8.9.3 of the amended JCT 2016.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from