In a case concerning the validity and effect of certain deeds
relating to pension increases, the High Court has handed down its
judgement. The case also considers the application of scheme
forfeiture clauses to arrears of underpayments.
The case, concerning the Axminster pension scheme
('Scheme'), was brought by the Scheme's independent
trustee. Many of the original issues were compromised by the
parties, meaning that the court was asked to approve the
compromise. The judgement and points considered by this article
relate to issues regarding arrears of benefits which would then be
calculated and payable. The arrears arose as a result of
underpayments in relation to pensions increase calculations and in
relation to equalisation of benefits under the Scheme. The key
questions considered by the Judge centred on statutory limitation
periods as well as the application of the Scheme forfeiture
rules.