In October 2011, the amendments to the Housing Grants, Construction and Regeneration Act ("HGCRA") came into force. They were specifically designed to give the payment provisions in the HGCRA more "teeth". If an employer failed to serve a timely payment or payless notice in response to a contractor's payment application, then the employer would become obliged to pay the amount of the application by default. This was because, in those circumstances, the amount of the application would become the "notified sum" which the employer would have to pay to the contractor.
Regarding payment disputes, the intention of the HGCRA was very
much that, if an adjudicator decided that an employer owed a
contractor a sum of money, the adjudicator's decision would be
temporarily binding on the parties, and would be quickly enforced
by the Courts, so that the money actually changed hands. The Courts
have described this as the "pay now, litigate later"
approach, which is obviously important to