PCSAs After Belong v Seddon: Pre-Contract Liabilities

Eversheds Sutherland
Eversheds Sutherland
Contributor
Eversheds Sutherland

Eversheds Sutherland

Eversheds Sutherland in Italy was founded more than 40 years ago and now has more than 80 lawyers...

View firm profile
Explore more from Eversheds Sutherland

This page contains standard legal disclaimer information and attorney contact details from Eversheds Sutherland's website. The content provides general information about the firm's legal notices, terms of use, and professional structure, along with contact information for Richard Hartigan.

United KingdomCorporate/Commercial Law

Belong (Construction) Limited v Seddon Construction Limited [2026] EWHC 1275: the High Court determines that “rights” and “liabilities” arising under a Pre-Construction Services Agreement (“PCSA”) remain enforceable after entry into the main building contract.

Why should I read this?

The Technology and Construction Court considered whether a contractor could avoid liability for breaches of a PCSA after entry into the main JCT building contract. The PCSA provided that rights and liabilities under the PCSA would be “subsumed into and be subject to” the main contract. HHJ Stephen Davies held that this did not extinguish accrued rights and liabilities under the PCSA. 

This is essential reading for anyone drafting, reviewing or advising on PCSAs in the construction sector. The decision also provides a useful framework for managing the transition from pre-construction services to the main contract.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from