Almost 50 years later, Lord Justice Coulson was asked to consider again the meaning of practical completion. Jesse Way takes up the story.

United KingdomCorporate/Commercial Law

In 1970, Viscount Dilhorne' in the case of City of Westminster v Jarvis, said that:

"The contract does not define what is meant by 'practically completed'. One would normally say that a task was practically completed when it was almost but not entirely finished; but 'Practical Completion' suggests that that is not the intended meaning and that what is meant is the completion of all the C construction work that has to be done."

Almost 50 years later, Lord Justice Coulson was asked to consider again the meaning of practical completion. Jesse Way takes up the story.

Earlier this year, the Court of Appeal delivered its judgment in Mears Limited v Costplan Services (South East) Limited & Ors [2019] EWCA Civ 502 ("Mears"). In Mears, the Court of Appeal had to determine two issues.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.