High Court presumes that a party does not intend to abandon a remedy to which it would not otherwise be entitled.

United KingdomCorporate/Commercial Law

High Court presumes that a party does not intend to abandon a remedy to which it would not otherwise be entitled

In a recent case the High Court held that, where liability for consequential loss is excluded, such exclusion will not be interpreted any more widely than was specifically stated in the contract. If consequential loss had been construed as widely as was asserted, it would have rendered the primary performance obligations in the contract effectively devoid of contractual content, there being no sanction for non-performance. It is now clear that the courts will not readily accept such a construction.

Providence, the licensee of an oil field, contracted with Transocean for the drilling of an appraisal well. Drilling delays were incurred and Transocean brought a claim against Providence in accordance with the day rates payable under the contract. Providence argued that the drilling rig and Transocean's performance were defective and that it should not have

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from