Due to the large number of offshore windfarm projects having
already been completed or being under construction in the German
Exclusive Economic Zone, we expect that German courts and arbitral
tribunals will be dealing with a number of disputes related to the
underlying contracts in the coming years.
Many of these contracts are based on standard forms such as the
BIMCO SUPPLYTIME 2005 or 2017, the BIMCO WINDTIME or LOGIC
contracts, all of which have been developed against the background
of English law. All of the above standard forms contain so called
"knock-for-knock" clauses, which set out a liability
regime for all dealings between the contractual parties. Under this
liability regime, damages and losses are not covered by the party
at fault but rather by each party incurring the respective loss,
irrespective of the nature or cause of the damage. This is based on
the assumption that any such losses and damages can and will be
insured and thus attempts to make the