On 31 October 2019, the UK Court of Appeal dismissed BritNed
Developments' appeal in which it sought to increase the award
of damages that the High Court made last year.1 Not only
is this the first claim of its kind to go to full trial, the
judgment is significant because the Court of Appeal set out the
correct approach to assessing follow-on competition damages
claims.
In a claim concerning ABB's participation in the alleged
power cables cartel, the High Court ordered ABB to pay to BritNed
damages of just over €13 million. This was significantly less
than the €200 million that BritNed had claimed. In a
subsequent supplementary judgment, the High Court reduced
BritNed's damages by 10% to € 11.7 million. For further
detail on the background, please refer to our previous
Advisories.2