BritNed Developments v. ABB : UK Court Of Appeal Reduces Damages On Appeal

Arnold & Porter
Arnold & Porter
Contributor
Arnold & Porter

Arnold & Porter

With over 1,000 lawyers across 16 offices worldwide, Arnold & Porter is renowned for its...

View firm profile
Explore more from Arnold & Porter

On 31 October 2019, the UK Court of Appeal dismissed BritNed Developments' appeal in which it sought to increase the award of damages that the High Court made last year.

United KingdomAntitrust/Competition Law

On 31 October 2019, the UK Court of Appeal dismissed BritNed Developments' appeal in which it sought to increase the award of damages that the High Court made last year.1 Not only is this the first claim of its kind to go to full trial, the judgment is significant because the Court of Appeal set out the correct approach to assessing follow-on competition damages claims.

In a claim concerning ABB's participation in the alleged power cables cartel, the High Court ordered ABB to pay to BritNed damages of just over €13 million. This was significantly less than the €200 million that BritNed had claimed. In a subsequent supplementary judgment, the High Court reduced BritNed's damages by 10% to € 11.7 million. For further detail on the background, please refer to our previous Advisories.2

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from