Whose Fault Is It Anyway? A Perspective Into Force Majeure In The UAE

Hadef & Partners
Hadef & Partners
Contributor
Hadef & Partners

Hadef & Partners

Shaping UAE law for over 45 years Hadef & Partners is a long-established UAE law firm with an...

View firm profile
Explore more from Hadef & Partners

The clauses of off plan real estate sales contracts in the UAE customarily contain "Force Majeure" clauses, however, they do not necessarily conform to the traditional concept of force majeure.

United Arab EmiratesReal Estate and Construction
Michael Lunjevich
Michael Lunjevich
Bianca Gracias
Bianca Gracias

In brief:

  • The clauses of off plan real estate sales contracts in the UAE customarily contain "Force Majeure" clauses, however, they do not necessarily conform to the traditional concept of force majeure. Such clauses typically include events in addition to acts of God and therefore they might be more appropriately called "Delay Event Clauses" i.e. an event that allows a person to delay performance.
  • Although the UAE Civil Code does not specifically address force majeure it does provide a judge scope to reduce onerous obligations on contracting parties in extenuating circumstances.
  • Developers and purchasers should pay attention to innocuous wording in so called "force majeure" clauses and shouldn't assume force majeure is so widely understood that it will cover all reasons for delay outside a parties' control.