The starting point for resolving construction disputes in the UAE is the contract, the applicable law, and the agreed dispute procedure. Article 818 of the Civil Transactions Law addresses defective or delayed work. Articles 821 to 824 address building defect liability, including a ten-year guarantee and a separate three-year claim period.
The 2025 Civil Transactions Law took effect on June 1, 2026. Earlier facts and transactions may require the former law under the applicable transitional rules.
Contract rules for resolving construction disputes in the UAE
- Defective or late work: The employer can give notice to correct within a reasonable period. After that, and after documenting the condition, he can terminate or have another contractor complete or correct the work at the first contractor's cost. He can terminate at once if repair is impossible, the delay is hopeless or the contractor shows he will not perform (Article 818).