Practical Side: How It's Done
When purchasing off-plan property in the UAE, buyers must be
aware of several key clauses within the Sale and Purchase
Agreements (SPAs). These standard clauses, used by most developers,
are vital in protecting buyers' interests and ensuring their
rights are upheld throughout the property transaction process. The
key clauses related to late delivery include:
The Completion and Passing of Risk
Clause outlines the developer's anticipated
completion date and permits an extension for specific reasons
outlined in the agreement, usually between 6-12 months. If the
property is not completed and deliverable beyond the extension
period, the SPA may be canceled. The clause also specifies the
buyer's financial obligations to become eligible for
possession once the property is complete and the risks associated
with the property transfer to the buyer only after handover.