You collect the keys to your Dubai apartment, arrange the furniture and prepare to move in. A few weeks later, the air-conditioning fails, water appears beneath the bathroom tiles, or cracks develop along a wall.
The developer calls it maintenance. Building management says it is inside your unit. You are left wondering who should pay.
When dealing with property defects in Dubai, responsibility depends on the cause, the affected component, the applicable contract and the relevant dates. A visible symptom alone rarely identifies the responsible party.
Quick answer: For Dubai jointly owned real property covered by Law No. 6 of 2019, Article 40 makes developers responsible for structural defects for ten years from the project completion certificate, and defective installations for one year generally from unit handover. If an owner refrains from taking possession, the installation period instead starts from the project completion certificate. Routine maintenance, misuse and later