Disruption costs claims on construction projects are known to
have a lower success rate than their rich cousin, the prolongation
costs claim. There are two main reasons for this: (1) a lack of
understanding of their nature and how they relate to other types of
additional cost claim; and (2) an inability to demonstrate their
essential ingredients.
Disruption is often referred to as inefficient working. This is
not far off the mark, but a more accurate definition is found in
the SCL Protocol which defines disruption as “disturbance,
hindrance or interruption to a Contractor's normal working
methods, resulting in lower productivity or efficiency.”
A useful simplification for distinguishing disruption from delay
is that ‘delay is not disruption, but disruption may lead to
delay'. In terms of how this translates into claims for
additional cost, claims for disruption costs are for the
contractor's direct additional costs due to the reduced
productivity, whereas