Testing The Legal Basis Of The Lack-of-purpose Argument

One of the most daunting prospects for an MEP sub-contractor – or, indeed, any sub-contractor – is the possibility of being held ransom to a pay-when-paid clause.

United Arab EmiratesLitigation, Mediation & Arbitration

One of the most daunting prospects for an MEP sub-contractor - or, indeed, any sub-contractor - is the possibility of being held ransom to a pay-when-paid clause.

Quite commonly included in MEP sub-contracts, this clause effectively dictates that the MEP sub-contractor will receive payment only within a given period of time, usually around 14 days, after such payment has been actually received by the main contractor. This type of provision is usually interpreted by main contractors as a carte blanche to simply avoid making payments due to the MEP sub-contractor, unless and until the corresponding payment has been received from the employer.

Under normal circumstances, this type of provision is nothing more than administrative in nature and should not cause any problems. However, in instances where there is an underlying dispute between the main contractor and the employer, delays in payment may ensue, which could indirectly affect the MEP sub-contractor. In those

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.