In a recent construction dispute under a DIAC
arbitration, between a main contractor (represented by our firm)
and an employer, a tribunal decided to appoint a tribunal expert,
after closure of proceedings and only a few weeks before the
deadline for issuing the final award, without any other event
occurring in the interim.
The dispute arose out of a construction contract where the
contractor claimed against the employer its prolongation costs for
extensions of time already awarded by the engineer, as well as for
its profit on variations carried out.
The contractor produced quantum expert evidence in support of
its claim which was unopposed by any corresponding quantum expert
evidence by the employer.