In a significant ruling that underscores the strict formalities
governing arbitration agreements under UAE law, the Dubai Court of
Cassation recently issued its final judgment in Case No.
445/2025/24, rejecting the appeal of a joint venture comprising a
Spanish multinational construction company and a leading Turkish
EPC contractor.
The dispute revolved around the enforcement of payment
obligations under subcontracting agreements in the Expo 2020 Metro
Line project, and more critically, the enforceability of an
arbitration clause embedded in unsigned contract annexes.
Background: Retention Dispute Over Completed
Works
The Respondent, a German contractor specialising in complex
civil and geotechnical engineering projects, filed Commercial Case
No. 3836/2023 before the Dubai Court of First Instance seeking
payment of AED 1,151,122.81, plus statutory interest, in relation
to retention sums withheld under two subcontracts executed as part
of the "Expo Link 2020