Who: Government of Nigeria; Governor of Enugu
State; Motir DuSable Power Investment (US renewable energy
investment firm).
What: Motir DuSable is establishing a 300MW
solar power plant in Nigeria's southern city of Enugu, capital
of Enugu State. The first part of the project is the construction
of a 100MW plant which is estimated to cost US$200million and
subsequently, the plant will be expanded to produce a further 200MW
at an additional cost of US$200million too1. The company
already has operations in Asia and other parts of Africa.
When: Phase I of the project should be
completed over the next 12-18months.
Why: Power generation remains a major challenge
across Nigeria and Enugu is no exception. The plan is to make Enugu
State a hub for energy generation and to create jobs through this
venture across the state. The addition of this solar facility will
see the government inch closer to reaching this goal, as the state
government also seeks to harness the