ARTICLE · 10 JANUARY 2025

Empowering The Future: Analysing Regulatory Policies To Catalyse Investment In Renewable Thermal Energy In Nigeria

Tope Adebayo LP
Tope Adebayo LP
Contributor
Explore more from Tope Adebayo LP

Recently, President Bola Ahmed Tinubu inaugurated the new 350 Mega Watt (MW) Gwagwalada Independent Thermal Power Plant (Phase 1), projected to be completed within three (3) years.

NigeriaEnergy and Natural Resources

Recently, President Bola Ahmed Tinubu inaugurated the new 350 Mega Watt (MW) Gwagwalada Independent Thermal Power Plant (Phase 1), projected to be completed within three (3) years. It is anticipated that the thermal plant will increase Nigeria's cumulative power by 3,600MW, and generate multiple foreign direct investments for the country. This is a laudable move by the President, as it demonstrates the political will to bring to fruition the administration's plan to boost power generation beyond the currently installed capacity of 12,000 MW.

Nigeria's transmission network currently consists of a wheeling capacity of 5,300 MW, higher than the average operational generation capacity of 3, 879 MW, which is far below the total installed generation capacity of around 12,522MW. This disparity between the installed and generation capacity is a result of the losses across the network, which reflects the critical infrastructure and operational challenges in the

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from