Timeframes for Review of the Award of Public Sector Contracts

On 8 September, the timeframe for reviewing the award of public sector contracts was clarified by S.I. No. 420 of 2010 (the "S.I."). The S.I. substituted a new Order 84A in the Rules of the Superior Courts so that it is now consistent with European law.

IrelandReal Estate and Construction
Kerri Crossen
Kerri Crossen
David Gunn
David Gunn

Order 84A of the Rules of the Superior Courts

On 8 September, the timeframe for reviewing the award of public sector contracts was clarified by S.I. No. 420 of 2010 (the "S.I."). The S.I. substituted a new Order 84A in the Rules of the Superior Courts so that it is now consistent with European law.

Order 84A now provides that the timeframes are those set out in Regulation 7 of the European Communities (Public Authorities' Contracts) (Review Procedures) Regulations 2010 and the European Communities (Award of Contracts by Utility Undertakings) (Review Procedures) Regulations 2010 (together the "Remedies Regulations").

Proceedings to review a public sector contract must be commenced 30 calendar days from when the claimant "knew or ought to have known" of the alleged infringement. The European Court of Justice ("ECJ") in its judgement in the Uniplex (UK) Limited v NHS Business Services Authority, Judgement (Case C – 406/08) set out that the limitation period should