ARTICLE · 13 SEPTEMBER 2021

Construction Law Update: High Court Rules That Adjudicator Has Jurisdiction In The Páirc Uí Chaoimh Dispute

The High Court has ruled in Kevin O'Donovan and Cork GAA v Dr. Bunni, James Bridgeman, and OCS One Complete Solution Ltd, which concerned the question of whether an adjudicator had jurisdiction to hear a dispute referred under the Construction Contracts Act 2013.

IrelandReal Estate and Construction

The High Court has ruled in Kevin O'Donovan and Cork GAA v Dr. Bunni, James Bridgeman, and OCS One Complete Solution Ltd, which concerned the question of whether an adjudicator had jurisdiction to hear a dispute referred under the Construction Contracts Act 2013.  The key issue before the court was whether the construction contract governing relations between the parties was a letter of intent OR the full contract subsequently entered into, on a date after commencement of the Act.

Background

The case concerned a dispute over payment for electrical works carried out by OCS One Compete Solution Ltd for Cork GAA at Páirc Uí Chaoimh. OCS referred a payment dispute for adjudication, and the Chairperson of the Panel of Adjudicators, Dr Bunni, appointed an adjudicator, James Bridgeman.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

This article contains a general summary of developments and is not a complete or definitive statement of the law. Specific legal advice should be obtained where appropriate.