Guidance From The Office Of Government Procurement Regarding The Public Works Contracts And Ex Gratia Payment Scheme

RDJ LLP
RDJ LLP
Contributor
RDJ LLP

RDJ LLP

RDJ is one of Ireland’s leading corporate law firms. With more than 300 employees and offices in...

View firm profile
Explore more from RDJ LLP

In this article, we look at the recent guidance that has issued regarding Public Works Contracts arising from the closure of all non-essential construction sites on 8 January 2021...

IrelandGovernment, Public Sector

In this article, we look at the recent guidance that has issued regarding Public Works Contracts arising from the closure of all non-essential construction sites on 8 January 2021 as part of the national effort to prevent the spread of Covid-19. The mandatory closure was given legal effect by the  Health Act 1947 (Section 31a - Temporary Restrictions) (Covid-19)(No. 10)(Amendment) Regulations 2021) (the "Measures") which provided for a limited list of essential construction activities to continue during the lockdown period, set to continue until at least 5 April 2021.

Guidance Issued on 12 February 2021

On 12 February 2021 the Office of Government Procurement ("OGP") issued a guidance note (the "Guidance") in respect of public works contracts ("PWCs") affected by the Measures dealing with the following matters:

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from