Supreme Court Looks For European Guidance On Constrained / Curtailed Electricity

William Fry LLP
William Fry LLP
Contributor
William Fry LLP

William Fry LLP

William Fry advises leading Irish and international companies, covering both the public and private...

View firm profile
Explore more from William Fry LLP

The Supreme Court has referred a number of questions concerning redispatch compensation arising under the governing framework for Ireland's internal electricity market.

IrelandEmployment and HR

The Supreme Court has referred a number of questions concerning redispatch compensation arising under the governing framework for Ireland's internal electricity market.

Background

In November 2024, the High Court set out its substantive decision in the 'GR Wind Farms' case regarding Ireland's rules on the dispatching of electricity generation and demand response, as set out in a Single Electricity Market Committee (SEMC) Decision (the Decision), in the context of Article 12 and Article 13 of EU Regulation 2019/943 (the Regulation). We previously covered the background to that judgment and some of the key relevant concepts here.

Following the Commission for Regulation of Utilities' (CRU) appeal of the High Court's decision, an oral hearing took place in the Supreme Court on 12 and 13 December 2024, following which the Supreme Court has made its first order of 2025, deciding to refer certain EU law questions raised in the case to the Court of Justice of the

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from