In the case of RGB Plastering Limited v Tawe Drylining and
Plastering Limited the TCC considered the validity of an
application for payment under the terms of the subcontract between
the parties. In particular, the court determined whether or not the
application could be relied on to recover monies in the absence of
any Payment Notice or Pay Less Notice, in true "smash and
grab" style. The case serves as a useful reminder of the
importance of adhering to contractual payment terms.
The Facts
RGB Plastering Limited (RGB) engaged Tawe Drylining (Tawe) as
the drylining subcontractor on a project in Portsmouth. The
subcontract set out a system for interim payments in clause 18 of
the terms and conditions and in the payment schedule. The latter
included a table setting out the relevant dates for each payment
cycle. These included for the April 2019 cycle that Tawe should
issue its application on 28th of that month and the valuation or
due date for such an application was