Ireland's leadership in data centre projects received a
significant boost this morning with the news that the Irish
Commercial Court ruled in favour of Apple's data centre in
Galway. The decision is very welcome for the economy in that
region and for the IDA's search for additional suitable sites
for large data centres across Ireland, launched in June 2017.
The Commercial Court today rejected the two challenges to the
planning permission for Phase 1 of the Apple data centre in
Athenry. There is an eight-phase masterplan for eight data halls on
the site.
The first case challenged the site selection and the extent of
the environmental assessment in the planning process.
It was argued that the planning permission for the
Phase 1 data hall would not have been granted if that phase were
not part of the wider project for eight future data halls.
Thus, the Court was asked to infer that planning permission was
granted on the basis that it was intended to complete