Guidelines For Monitoring Of Projects And Issuance Of Provisional Completion And Completion Certificates For EPC/HAM/BOT Contracts

JSA Advocates & Solicitors
JSA Advocates & Solicitors
Contributor
JSA Advocates & Solicitors

JSA Advocates & Solicitors

Established in 1991 Our services: JSA is a leading law firm in India with more than 600...

View firm profile
Explore more from JSA Advocates & Solicitors

NHAI, in its policy circular dated May 24, 2024, issued guidelines for proper monitoring of projects and issuance of Provisional Completion Certificate ("PCC") and Completion Certificate ("CC") to the concessionaires/contractors under the concessionaire agreement.

IndiaTransport

NHAI, in its policy circular dated May 24, 2024, issued guidelines for proper monitoring of projects and issuance of Provisional Completion Certificate ("PCC") and Completion Certificate ("CC") to the concessionaires/contractors under the concessionaire agreement. NHAI observed the following non adherence in monitoring of project and issuance of PCC/CC: 1. AE and RO/PD officials are not supervising the work and tests on completion in several cases which lead to incorrect issuance of PCC/CC; and 2. such tests on completion and other compliances were not being submitted in different formats. Procedurally, to obtain PCC/CC from NHAI, the concessionaire/contractor make a request to the IE to conduct tests as per the provisions of the concession agreement and the IE/AE also informs the PD/RO, NHAI to witness the tests.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from