1. INTRODUCTION
The Maharashtra Authority for Advanced Ruling (the
"AAR") recently held in an advance
ruling that goods and services tax
("GST") is applicable on liquidated
damages imposed on delayed performance or non-performance of
contracts executed in relation to certain services.1
The decision comes in response to the application (the
"Application") for advance ruling made
by the Maharashtra State Power Generation Company (the
"Applicant") under section 97 of the
Central Goods and Services Act, 2017 (the "GST
Act").
2. THE RULING
Under section 97 and section 100 of the GST Act, any person may
obtain an advance ruling from the relevant authorities (the
Authority for Advance Ruling and/or the Appellate Authority) on one
or more questions in relation to the supply of goods or services
(or both) being undertaken or proposed to be undertaken by such
applicant.