Introduction
“No Claim Certificate” or “No Due Certificate” refer to a Condition Precedent placed by the Employer before the Contractor for the release of their payment.
Construction and Infrastructure Projects are complicated and often run over and above the schedule, Contractor incurs huge losses due to delays, usually caused by the employer. In such situations, the employer presents a “No Claim Certificate” to the Contractor to be signed before release of their payment. The Contractor caught in a cash flow crunch signs the dotted lines in order to get their payment released, which are sometimes underestimated figures. Subsequently, Weeks or Months later, the Contractor raises dispute claiming, “Economic Duress” or “Coercion” while signing the “No Claim Certificate”. The Employer on the other hand takes the defence of “Accord & Satisfaction”; claiming that the Contract was discharged as soon as the Certificate was signed and Bills were cleared accordingly.