Delhi High Court Upholds Arbitral Tribunal Findings On Delay Analysis Using The Critical Path Method And Reiterates Limits Of Section 34 Review

JSA Advocates & Solicitors
JSA Advocates & Solicitors
Contributor
JSA Advocates & Solicitors

JSA Advocates & Solicitors

Established in 1991 Our services: JSA is a leading law firm in India with more than 600...

View firm profile
Explore more from JSA Advocates & Solicitors

The Delhi High Court (“Delhi HC”), in Ircon International Limited vs. Afcons Infrastructure Limited1, has provided important guidance on the evaluation of critical path analysis and delay attribution in construction disputes. The Delhi HC examined whether an arbitral tribunal’s findings on delay, based on project schedules and critical path analysis, could be interfered with under Section 34 of the Arbitration and Conciliation Act, 1996 (“Arbitration Act”).

IndiaLitigation, Mediation & Arbitration

The Delhi High Court (“Delhi HC”), in Ircon International Limited vs. Afcons Infrastructure Limited1, has provided important guidance on the evaluation of critical path analysis and delay attribution in construction disputes. The Delhi HC examined whether an arbitral tribunal’s findings on delay, based on project schedules and critical path analysis, could be interfered with under Section 34 of the Arbitration and Conciliation Act, 1996 (“Arbitration Act”). While considering this, the Delhi HC discussed in detail the jurisprudence relating to delay analysis in construction contracts, including how tribunals should attribute responsibility for delays affecting project completion.

Brief facts

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from