In a commercial contract, a tender is procured upon estimation
of prices of material and labor to be incurred in future. However,
these prices are susceptible to change due to reasons beyond the
control of either party. Such unforeseen change in prices, which
may shake the very foundation of the bargain, which parties entered
into, may lead to frustration of contract, which in turn leads to
termination of contract. To avoid such a situation, an escalation
clause is added into the contract, which takes into account any
future changes in prices of labor and material.
It is a cardinal principle of arbitration, that the arbitrator
derives his authority from the terms of the contract and an award
passed in contravention of such terms of contract is without
jurisdiction and is liable to be set aside. However, there are
several instances where contract does not provide for escalation
clause and the contract is extended beyond completion period
because of no fault of