On August 13, 2020, the Ministry of New and Renewable Energy issued an office memorandum regarding extension of time in Scheduled Commissioning Date of Renewable Energy Projects considering disruption due to ...

IndiaEnergy and Natural Resources

Blanket Extension for Renewable Energy Projects

Background:

On August 13, 2020, the Ministry of New and Renewable Energy (MNRE) issued an office memorandum (OM) regarding extension of time in Scheduled Commissioning Date of Renewable Energy (RE) Projects considering disruption due to lockdown resulting from COVID-19. The OM supersedes the OMs dated April 17, 2020 and June 30, 2020.

What are the features of the OM?

  • All implementing agencies of the MNRE are to treat lockdown due to COVID-19 as Force Majeure.
  • State Renewable Energy Departments (including agencies under Power/Energy Departments of States, dealing in renewable energy) may also treat the lockdown as Force Majeure and consider granting appropriate extension of time on account of such lockdown.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from