On 30 March 2026, India lost about 34 GWh of renewable generation in a single day, not because the sun did not shine or the wind did not blow, but because there was not enough transmission capacity to carry the power. The plants were ready, the power was available, and yet it went nowhere.
The short answer to the question in the title is that it depends on why the power could not be evacuated. Where a load despatch centre curtails a must-run renewable plant for reasons other than grid security, Indian law and regulators have placed the cost on the procurer, which must compensate the generator at the tariff agreed in the power purchase agreement ("PPA"). Where the problem is that transmission infrastructure is not ready, or that the plant has only temporary access to the grid, the position is far less settled, and much of the risk falls back on the developer unless its PPA expressly allocates it elsewhere.