The MNRE vide its advisory dated 21.08.20261 has advised Renewable Energy Implementing Agencies (“REIAs”) to consider extension of Scheduled Commencement of Supply Date (“SCSD”) and Scheduled Commissioning Date (“SCD”) on account of Force Majeure event due to West Asia Situation.
The advisory of MNRE relies upon the advisory issued by the Ministry of Finance (“MoF”) vide Office Memorandum dated 29.04.2026, wherein the MoF has stated that West Asia situation shall be treated as “war” for Force Majeure purposes. In light of the same, MNRE has further noted that the Standard Bidding Guidelines for procurement of renewable power, issued under Section 63 of the EA 2003, require Power Purchase Agreements (“PPA”) to contain provisions on Force Majeure definitions, exclusions, applicability and available relief, and that “war” is generally included therein as a Force Majeure event.