MNRE Has Issued Advisory For Extension Of Timelines For Implementation Of Renewable Energy Power Projects Due To Force Majeure

Sagus Legal
Sagus Legal
Contributor
Sagus Legal

Sagus Legal

We are a full-service law firm providing comprehensive legal advisory and advocacy to clients. Our...

View firm profile
Explore more from Sagus Legal

The MNRE vide its advisory dated 21.08.2026 has advised Renewable Energy Implementing Agencies (“REIAs”) to consider extension of Scheduled Commencement of Supply Date (“SCSD”) and Scheduled Commissioning Date (“SCD”) on account of Force Majeure event due to West Asia Situation.

IndiaEnergy and Natural Resources

The MNRE vide its advisory dated 21.08.20261 has advised Renewable Energy Implementing Agencies (“REIAs”) to consider extension of Scheduled Commencement of Supply Date (“SCSD”) and Scheduled Commissioning Date (“SCD”) on account of Force Majeure event due to West Asia Situation.

The advisory of MNRE relies upon the advisory issued by the Ministry of Finance (“MoF”) vide Office Memorandum dated 29.04.2026, wherein the MoF has stated that West Asia situation shall be treated as “war” for Force Majeure purposes. In light of the same, MNRE has further noted that the Standard Bidding Guidelines for procurement of renewable power, issued under Section 63 of the EA 2003, require Power Purchase Agreements (“PPA”) to contain provisions on Force Majeure definitions, exclusions, applicability and available relief, and that “war” is generally included therein as a Force Majeure event.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from