GERC Grants First-of-its-Kind Extension For Power Evacuation Infrastructure

Dentons
Dentons
Contributor
Dentons

Dentons

The Firm Across over 80 countries, Dentons helps you grow, protect, operate and finance your...

View firm profile
Explore more from Dentons

GERC, in one of the first of its kind matter, extended completion date of the power evacuation infrastructure recognising occurrence of the unforeseen events...

IndiaEnergy and Natural Resources

GERC, in one of the first of its kind matter, extended completion date of the power evacuation infrastructure recognising occurrence of the unforeseen events

In one of the first of its kind matter before Gujarat Electricity Regulatory Commission ("GERC"), it allowed extension of 465 days to a renewable energy developer for construction of evacuation infrastructure.

Cleanmax Vayu Urja Private Limited, a renewable energy developer ("Cleanmax") is setting up a 100MW renewable energy power plant at Devpur Ranuja, Gujarat ("Power Plant") got its right to get connected with the transmission asset of GETCO. As per the applicable laws, Cleanmax was required to complete the evacuation infrastructure within the timeline specified by the Commission, failing which its right to get connected with GETCO's transmission asset would be revoked. Connectivity is a major element of any power project and without connectivity, any power developer will not be able to supply its power

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from