Draft Regulations For Verification Of Captive Status Of Generating Plants/consumers

JSA Advocates & Solicitors
JSA Advocates & Solicitors
Contributor
JSA Advocates & Solicitors

JSA Advocates & Solicitors

Established in 1991 Our services: JSA is a leading law firm in India with more than 600...

View firm profile
Explore more from JSA Advocates & Solicitors

The Tamil Nadu Electricity Regulatory Commission ("TNERC"), vide notification dated June 24, 2024, had issued the ‘Draft TNERC (Verification of Captive Status of Generating Plants /Consumers) Regulations.

IndiaEnergy and Natural Resources

The Tamil Nadu Electricity Regulatory Commission ("TNERC"), vide notification dated June 24, 2024, had issued the 'Draft TNERC (Verification of Captive Status of Generating Plants /Consumers) Regulations, 2024' ("Draft Verification Procedure") for seeking views/comments/suggestions from the public. The Draft Verification Procedure, proposed under the Electricity Act, 2003, aims to specify the methodology for verification of status of captive generating plants ("CGP") and captive users located within the State.

Key highlights of the Draft Verification Procedure

  • Scope and extent: The Draft Verification Procedure will apply to all CGPs and captive users throughout the State of Tamil Nadu.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from