MNRE Notified A Limited Window Extension To Net Metering And Open Access RE Power Projects Exemption From ALMM List-II Till 31.12.2026

Sagus Legal
Sagus Legal
Contributor
Sagus Legal

Sagus Legal

We are a full-service law firm providing comprehensive legal advisory and advocacy to clients. Our...

View firm profile
Explore more from Sagus Legal

MNRE by Office Memorandum dated 18.07.2026 notified an extended limited window for Net-Metering and Open Access renewable projects, for exemption from Approved List of Models and Manufacturers List-II (for solar PV cells) till 31.12.2026.

IndiaEnergy and Natural Resources

MNRE by Office Memorandum dated 18.07.2026 (“Extension OM”)1 notified an extended limited window for Net-Metering and Open Access renewable projects, for exemption from Approved List of Models and Manufacturers (“ALMM”) List-II (for solar PV cells) till 31.12.2026.

In accordance with paragraph 8 of MNRE’s O.M. No. 283/59/2024-GRID SOLAR dated 09.12.2024, all the Net-Metering projects and Open Access RE power projects, which get commissioned on or after 01.06.2026, are mandatorily required to source their solar PV modules from ALMM List-I and solar PV cells from ALMM List-II. MNRE by the Extension OM, has notified that there shall be no blanket extension in the applicability of ALMM List-II for solar power projects. However, a limited window has been provided for Net-Metering projects and Open Access RE power projects, whereby such projects can be commissioned with exemption from ALMM List-II, till 31.12.2026.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from