MNRE by Office Memorandum dated 18.07.2026 (“Extension OM”)1 notified an extended limited window for Net-Metering and Open Access renewable projects, for exemption from Approved List of Models and Manufacturers (“ALMM”) List-II (for solar PV cells) till 31.12.2026.
In accordance with paragraph 8 of MNRE’s O.M. No. 283/59/2024-GRID SOLAR dated 09.12.2024, all the Net-Metering projects and Open Access RE power projects, which get commissioned on or after 01.06.2026, are mandatorily required to source their solar PV modules from ALMM List-I and solar PV cells from ALMM List-II. MNRE by the Extension OM, has notified that there shall be no blanket extension in the applicability of ALMM List-II for solar power projects. However, a limited window has been provided for Net-Metering projects and Open Access RE power projects, whereby such projects can be commissioned with exemption from ALMM List-II, till 31.12.2026.