Supreme Court Of India Revisits The Measure Of Damages For Delay In Completion Of Works Contract And The Hudson Formula In Building And Engineering Contracts

UNIBROS was awarded a works contract by ALL INDIA RADIO (AIR) to construct an office building.

IndiaCorporate/Commercial Law

Supreme Court of India1 revisits the measure of damages for delay in completion of works contract and the Hudson formula in Building and Engineering Contracts.

Brief facts

UNIBROS was awarded a works contract by ALL INDIA RADIO (AIR) to construct an office building. The construction was scheduled to be completed in 1 year but suffered a delay of 3-1/2 years. Disputes arose between the parties regarding the compensation for delay in completion of construction. UNIBROS invoked arbitration. Amongst the various claims before the arbitral tribunal, UNIBROS claimed INR 2,00,00,000/- for loss of profit endured due to UNIBROS retention on the contract without any corresponding increase in monetary benefits.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from