Section 63 of the Electricity Act, 2003 deals with procurement of power and determination of tariff for the supply of electricity.

IndiaCorporate/Commercial Law

Background:

The Electricity Act, 2003 (hereinafter referred to as "the Act") did away with 3 erstwhile legislations namely, the Indian Electricity Act, 1910, the Electricity (Supply) Act, 1928 and the Electricity Regulatory Commissions Act, 1998 paving the way for a new regime for generating and supply of electricity was provided for.

Section 63 of the Electricity Act, 2003 deals with procurement of power and determination of tariff for the supply of electricity. A process of bidding is followed to determine this tariff for which tenders are invited. Based on a pre-disclosed criterion the best possible tariff is followed in order to arrive at the lowest tender as decided amongst the participating bidders in a transparent bidding process.