ARTICLE · 17 FEBRUARY 2022

Goods And Services Tax (GST) Implications On ‘Liquidated Damages

S&A Law Offices
S&A Law Offices
Contributor
S&A Law Offices

S&A Law Offices

S&A Law Offices is a full-service law firm headquartered in Delhi NCR. The firm has 300+...

View firm profile
Explore more from S&A Law Offices

‘Liquidated Damages' means a compensation specified under the contract agreed between the parties for an estimated loss and which is required to be paid upon failure of either party to perform its obligations.

IndiaCorporate/Commercial Law

'Liquidated Damages' means a compensation specified under the contract agreed between the parties for an estimated loss and which is required to be paid upon failure of either party to perform its obligations. It is important to note that 'Liquidated Damages' is not defined under the Indian Contract Act, 1872. However, there are provisions that protect rights and privileges of parties in case of non-performance of contract by either of the parties.

DIFFERENCE BETWEEN LIQUIDATED DAMAGES AND UNLIQUIDATED DAMAGES

Liquidated damages are considered as compensation which is already agreed upon by the parties in a contract. On the other hand, unliquidated damages are awarded by a consequence of an order passed by a court or tribunal and such compensation is not determined or agreed in a contract entered between parties.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from